How long will it take? When will we reach certain milestones? Check out the handy timeline below!
+/- 30 days for Owners/Builder to complete selections
+/- 2 weeks for the home designer to complete the floor plans and submit them to the structural engineer
+/- 30 days for the structural engineer and home designer to have the plans completed
+/- 2 weeks after receiving engineered plans to have permit application ready to submit
+/- 30 days after receiving engineered plans for Design or Architectural Review Committee (if applicable)
+/- 30 days for local building department to review permit application
+/- 45 days – Site prep, Excavation, Footings, Foundation, Laterals
+/- 45 days – Framing, Rough Electrical, Rough Plumbing, Rough Heat, Windows, Ext. Doors, Roof
+/- 45 days – Exterior Finishes, Insulation, Drywall, Finish Work, Cabinets, Flooring, Finishes
+/- 15 days – Final inspections, Walk-Through, Punch-List Items
(This is a generic timeline and will vary with amount of custom features and overall square footage)